STAR Protected

EventQA_JetMeeting_20140603

The presentation is here

FGT Cosmic-ray test stand preparation

 

PWGC Meeting

2014-06-03 11:00
2014-06-03 12:30
America/New York
Tuesday, 3 June 2014
, at 15:00 (GMT), duration : 01:30

Agenda Items

  1. Run 14 - ongoing run: update by the period coordinator (Shusu Shi)
  2. Run 14 - upcoming h+Au run: input from the PWGs
  3. QM'14 "debriefing". Feedback and possible action points.
  4. RCF disk space poll -- feedback from PWGs requested
  5. AOB

SeeVogh details

Title:          STAR PWGC Meeting
Description:    PWGC conveners' weekly meeting
Community:      STAR
Password:       starpwgc
Meeting type: Open Meeting (Round Table)

Meeting Access Information:
- Meeting URL
   SeeVogh R.N.
http://research.seevogh.com/join?meeting=3D3D3D3DMaMDMt222uDvD89D9iDI9a
   EVO International
- Password: starpwgc
- Phone Bridge
    ID: 100 3600
    Password: 8682

SeeVogh Research Network Phone Bridge Telephone Numbers:
---------------
- USA (Caltech, Pasadena, CA)
   +1 626 395 2112

- USA (BNL, Upton, NY)
   +1 631 344 6100

- Skype (tm) (World-wide)
   evo.phone
   See: http://evo.caltech.edu/evoGate/Documentation/extclient/skype/skype.html

Run 9 200GeV Dijet Asymmetry: Asymmetry Systematics Summary

This page details the evaluation of the systematics for the dijet asymmetry measurement ...

HFT pre-cd4 prepartion

2014-06-10 09:00
America/New York
Tuesday, 10 June 2014
, at 13:00 (GMT), duration : 00:00
 There is a HFT f2f meeting at LBL on Tuesday June 10 in order to prepare for the pre-cd-4 meeting on July 31. That meeting will be a half day video conference with DOE,

Access to LBL

the pre-CD4 meeting will take place on June 10 at LBNL. We have reserved the Pers Hall Annex for the meeting. 
Please arrange for your lodging. Please let Lady (LBonifacio@lbl.gov) know when you will be at LBL so that she can arrange for a gate pass for you.

Room reservation:




A preliminary suggested

2014 Shutdown activities

In this blog entry, I will try to keep thoughts on necessary or suggested activities for the 2014 shutdown period.  It will likely be somewhat jumbled for a while, as initially it is just a brain

MIPs: Exploring an iterative fit

 

Questions to address in 2010 Cross Section Calculation

Bill's study of the ratio of e+e- to J/Psi cross sections:

base fabrication SpreadSheet

 

Transversity Talk Draft

Run 9 200GeV Dijet Asymmetry: Asymmetry Summary

A summary of the 2009 dijet asymmetries ...

Figure 1: The dijet yields in each mass bin for each spin bit.

HFT-HLT-CA

HFT-CA tracker standalone version

HF PWG Meeting Minutes by Zhenyu - 2014/05/29

Two items were discussed briefly today. One was about the 

PXL Alignment with Low Luminosity Zero Field Data

 This describes the procedure and results of the HFT/PXL sector alignment using the low luminosity data taken on day 100 (April 10th).

IST calibration update

Speaker : Babak Abi ( UIC )


Talk time : 21:25, Duration : 00:20

 

A_LL Consistency Checks

This page collects the results of various consistency checks for ALL calculation over Run13 data

Direct photons: summary for spin PWG

IST Sti geometry

 Updated IST Sti geometry:

Overview of StRoot FMS clustering code for reviewers

The FMS clustering code reconstructs possible photons ("points") from energy depositions ("hits") in groups ("clusters") of FMS towers.

bulkcorr update on BES v3

The new material in the update are v3 for pions only and v3 calculated from the transverse energy. Some discussions are added.