Monday Plenary Session
Updated on Thu, 2007-10-04 13:29. Originally created by dunlop on 2007-10-04 13:29.Time | Talk | Presenter |
---|---|---|
09:00 | Welcome and Overview ( 00:30 ) 1 file | James Dunlop |
09:30 | Production plans and analysis bottlenecks ( 00:30 ) 1 file | Jerome Lauret (BNL) |
10:00 | Overview and status of Embedding ( 00:15 ) 1 file | Olga Barannikova (UIC) |
10:15 | dE/dx status in Run VIII, issues and resolutions ( 00:15 ) 1 file | Yuri Fisyak (BNL) |
10:30 | Coffee break ( 00:15 ) | |
10:45 | Report from the committee on DSM utilization in run 8 ( 00:15 ) 1 file | Thomas Ullrich (BNL) |
11:00 | Intriguing energy and centrality dependences in the spectra and correlation structures from Au+Au collisions ( 00:30 ) 1 file | Michael Daugherity (UTA) |
11:30 | Investigating near-side 3-particle correlations in eta ( 00:30 ) 1 file | Pawan Kumar Netrakanti (Purdue) |
October 2007 STAR Analysis Meeting
Updated on Thu, 2007-10-04 13:28. Originally created by dunlop on 2007-10-04 13:28. 2007-10-15
2007-10-19
Etc/GMT-4
from Monday, 15 October 2007 to Saturday, 20 October 2007
Brookhaven National Laboratory
Brookhaven National Laboratory
Conference organizing committee information : James Dunlop
Conference duration: 5 days
October 2007 STAR Analysis Meeting
»
Combinatorics Within Jets: First Looks
Updated on Thu, 2007-10-04 14:05. Originally created by ahoffman on 2007-10-04 13:26.
DNP 2007 Inclusive Hadron Talk
Here are the powerpoint and pdf versions of my slides for DNP.
Pile-Up Studies
Updated on Wed, 2007-10-03 10:28 by testadmin. Originally created by margetis on 2007-10-03 10:15. Under:This page is for documentation of pile-up work. Pile-Up refers to
AOB
Updated on Wed, 2007-10-03 10:10. Originally created by testadmin on 2007-10-03 10:10.Speaker : All ( All )
Talk time : 12:45, Duration : 00:15
Drupal modules additions
Updated on Wed, 2007-10-03 11:12 by chajecki. Originally created by testadmin on 2007-10-03 10:10.Speaker : Zbigniew Chajecki ( OSU )
Talk time : 12:35, Duration : 00:10
STATUS of (installed) Drupal modules for STAR
EMC bug, plan for fix
Updated on Wed, 2007-10-03 10:08. Originally created by testadmin on 2007-10-03 10:08.Speaker : Victor Perevoztchikov, Jerome Lauret ( BNL )
Talk time : 12:20, Duration : 00:15
Calibration check point: dE/dx, SVT alignement
Updated on Wed, 2007-10-03 11:06 by genevb. Originally created by testadmin on 2007-10-03 10:07.Speaker : Gene Van Buren ( BNL )
Talk time : 12:05, Duration : 00:15
TPC dEdx
- Cropping off edges of sectors cleaned up the calibration a little.
PWG feedback on dE/dx resolution requirements
Updated on Wed, 2007-10-03 10:06. Originally created by testadmin on 2007-10-03 10:06.Speaker : James Dunlop ( BNL )
Talk time : 12:00, Duration : 00:05
Data Sets/Chain Options/Geometry Tags
Updated on Fri, 2007-11-16 15:57. Originally created by margetis on 2007-10-03 10:04. Under:Working Towards a Photon Cross Section
Updated on Tue, 2007-10-02 14:17. Originally created by rcorliss on 2007-10-02 10:06.A schematic view of a cross section is:
Patch Pixel prototype
Updated on Thu, 2007-11-15 14:28. Originally created by margetis on 2007-10-01 18:44. Under:The initial study for a Pixel prototype (patch) was done in MathCAD by Howard Wieman.
Hand Calculations-Formulas by H.Wieman/Gene VB/Victor P./
Updated on Wed, 2007-10-10 11:40. Originally created by margetis on 2007-10-01 18:12. Under:WARNING: Many pages in Howard's area can only be viewed by IE or Safari browsers.
Hand Calculations by J. Thomas
Updated on Tue, 2009-04-07 19:06. Originally created by margetis on 2007-10-01 17:55. Under: The area where most recent talks/results/ were presented is at
rnc.lbl.gov/~jhthomas/public/HFT/
Embedding Notes, Sept 28, 2007
Updated on Fri, 2007-09-28 18:15. Originally created by andrewar on 2007-09-28 18:15.Requests #1154003721 and #1154003633 (Upsilon and J/psi into Pythia+pp)
Data-MC comparison: Zgg
Updated on Fri, 2007-09-28 17:34. Originally created by ahoffman on 2007-09-28 17:20.Data Cuts:
L2Gamma Triggered Events
BBC timebin 6 - 9
Pt > 5.2
No Charged Track Association
1 SMD strip good in each plane
Load Balancer Connection
Updated on Tue, 2009-05-05 13:25 by testadmin. Originally created by deph on 2007-09-28 10:52. Under:The load balancer makes its decision as to which node to connect to, based on the number of active connections on each node.
Run 8 preparation, meeting #1
Updated on Fri, 2007-12-14 12:53 by testadmin. Originally created by jeromel on 2007-09-28 10:40. 2007-09-28 14:00
2007-09-28 15:00
Etc/GMT-5
Friday, 28 September 2007
1-189, at 18:00 (GMT), duration : 01:00
1-189, at 18:00 (GMT), duration : 01:00
Phone information below
In the US, call 1-605-475-8500
International, call
In Austria: 0820 4000 1572
In Belgium: 070 35 9987
In France: 0826 100 275
In Germany 01805 00 7646
In Ireland: 0818 270 032
In Italy: 0848 390 172
In Spain: 0902 886 048
In Switzerland: 0848 560 152
In UK: 0870 738 0760
In Netherlands: 0870 001 931
Enter Conference Room Number : 5343115
S+99008275343115
In the US, call 1-605-475-8500
International, call
In Austria: 0820 4000 1572
In Belgium: 070 35 9987
In France: 0826 100 275
In Germany 01805 00 7646
In Ireland: 0818 270 032
In Italy: 0848 390 172
In Spain: 0902 886 048
In Switzerland: 0848 560 152
In UK: 0870 738 0760
In Netherlands: 0870 001 931
Enter Conference Room Number : 5343115
S+99008275343115
AOB - Geometry updates, MC comparisons with Hand calculations etc
Updated on Thu, 2007-09-27 16:40. Originally created by margetis on 2007-09-27 16:39.Speaker : Spiros and All
Talk time : 01:50, Duration : 00:10