- videbaks's home page
- Posts
- 2025
- February (1)
- 2024
- 2023
- 2022
- 2021
- 2020
- 2019
- 2018
- December (1)
- November (2)
- October (1)
- September (1)
- August (1)
- July (4)
- April (3)
- March (1)
- February (2)
- January (1)
- 2017
- 2016
- November (1)
- September (2)
- August (2)
- July (1)
- June (1)
- May (1)
- April (1)
- March (1)
- February (1)
- January (1)
- 2015
- 2014
- 2013
- 2012
- 2011
- 2010
- November (3)
- 2009
- My blog
- Post new blog entry
- All blogs
HFT installed info
Hi
It has been brought up now a couple of times what the HFTs installation were.
This is the brief summary and confirmed by looking at the HFT monthly project reports
Run-12:
The HFT support cylinders with the ø 3" beampipe & FGT (west) was installed. 4 FGT disks
Run-13
HFT support with ø 4 cm beampipe, PXL support was installled
6FGT disks. PXL (reduced # sectors 3/10 installed part of run.
Installed on May 8, 2013.
Run-14 , 15 and 16
Full HFT, PXL,IST SSD ø4cm beam pipe
Run-17 to Run 25
Old CF cone and ø 3" beampipe